Cherry Hill Public Schools is taking corrective action after discovering that newly installed door pulls at several school entrances do not meet accessibility requirements.
The issue was discussed during the Nov. 10 Board of Education meeting, when district officials addressed concerns involving the main entrance and newly constructed accessible cafeteria entrances at Rosa Middle School.
Business Administrator Jason Schimpf explained that the district worked with its architectural firm, Garrison Architects, and civil engineers to investigate the concerns and confirmed that some of the specified door hardware did not meet accessibility standards.
Garrison Architects has accepted financial responsibility for replacing the noncompliant hardware with door pulls that meet Americans with Disabilities Act (ADA) requirements.
The replacements will extend beyond Rosa Middle School to recently renovated entrances at Beck and Carusi middle schools, along with Johnson, Barton, Kingston and Sharp elementary schools.
Board members questioned how the district would ensure that similar issues would not arise during future construction projects funded through the Cherry Hill Tomorrow bond referendum.
Schimpf emphasized that district officials are continuing to work with Cherry Hill Township’s code office and construction professionals to monitor compliance throughout the renovation process.
“I have full confidence in ensuring that all of our future projects are fully compliant with ADA,” Schimpf said.
He added that when accessibility concerns are identified, the district’s priority is to address them promptly.
The district is working to complete the hardware replacements as soon as possible, with Garrison Architects covering the associated costs.